  3/25/2008 from County Reps


      From: "Dorothy Toth Beasley" <beasleydt@bellsouth.net>
To: <teeth@mindspring.com>,
        <CLystlund@AtlanticSouthernBank.com>,
        <shanberry@stratford.org>,
        <FISCHER_DP@Mercer.edu>,
        <dmbx1@cox.net>
Cc: "Rick Chellman" <chellman@tndengineering.com>,
        "Donna Thompson" <donna@henningmediation.com>
Subject: Fw: Forest Hill Road
Date: Tue, 25 Mar 2008 17:03

Dear Residents' Representatives:

Forwarded herewith is the response of Moreland Altobelli, on behalf of the
County, to your submission of March 19 which was accompanied by Mr.
Chellman's substitute file of the same date.  Please review it at your
earliest convenience.  I would like to discuss this with you before you
prepare your reply, if that would be agreeable to you.  If best is evening
due to your schedules, I can call at any time tomorrow evening (Wednesday),
or Thursday after 8 pm, or Sunday evening at any time.  If Friday is the
only time convenient for you, I will change my schedule to meet by phone
then.  If Saturday is best, any time during the day is fine.

Your reply to the forwarded message will be due by close of business on
Monday, March 31.

Best regards,
Dorothy Toth Beasley
Mediator

-- Original Message -----
From: "Tonya Davis" <tdavis@maai.net>
To: "Dorothy Beasley" <beasleydt@bellsouth.net>
Cc: "Linda McNulty" <lmcnulty@maai.net>
Sent: Tuesday, March 25, 2008 1:36 PM
Subject: Forest Hill Road


> Please distribute to the Community Representatives
>
> Tonya Davis
> Moreland Altobelli
> 111 Third Street, Suite 230
> Macon, GA 31201-0502
> 478-755-0000 (phone)
> 478-744-0778 (fax)

 
Mediation_MAI_Response20080312.htm
Mediation_MAI_Response20080306.htm

  

Document

TO: Forest Hill Road Representatives


FROM: Bibb County Representatives


SUBJECT: Forest Hill Road Mediation Response to Citizens (3-19-08)


DATE: 3/25/2008


I’m sorry about your misinterpretation of our reaction at the mediation session on February 28th. The presentation of the two typical sections for Forest Hill Road was certainly unexpected by our group. I realize it was an enormous and dramatic change for your group to acquiesce that improvements are needed all along Forest Hill Road.


Our group is very firm that a three-lane section is needed north of Wimbish Road. As requested by your response of March 19th, we have reviewed your proposal again with an open mind and in more detail on the 52-foot wide section. Attached for your convenience is another copy of Residents Drawing No. 1 showing the 52-foot wide footprint. We have produced an alternate drawing labeled County Drawing No. 4, which gives each of the groups a 52 foot wide section. Please notice the following similarities:


Drawing No.

Footprint

Paving

Width

Shoulder

Width

Sidewalk Width

No. lanes

Residents Drawing No. 1

52 feet

32 feet

10 feet

5 feet

2

County Drawing No. 4

52 feet

32 feet

10 feet

5 feet

3


We think these two sections are too close not to have agreement on. We think the over four million vehicles traveling this road each year need the safety that the three lanes can provide. Left turn lanes are needed at each of the 15 intersecting side streets and 85 private driveways. This is as far as our group is prepared to go as far as compromising safety on this section.


Our offer to reduce the footprint of the four-lane section from 86 feet 7 inches to 79 feet 5 inches is as far as we are willing to compromise this typical section. This is the best we can do.


Reducing the design speed of both projects from 45 mph to 35 mph is not reasonable at this late date. However, as you know, both projects will have a posted speed limit of 35 mph. This will be a reduction from the now posted 45 mph to 35 mph when construction is completed.


In response to the concerns expressed in the Resident’s Response of March 19th contained in the initial position paper, we think these concerns were addressed in the Environmental Assessment and the Finding of No Significant Impact prepared by environmentalists, historians, and scientists working on the design of this project. I think your group has a copy of these documents. The impact to historical properties, streams, ecology, air, noise, wetlands, endangered species, water quality, land use, relocations, economic/social, utilities, and hazardous wastes were identified and addressed in these documents. These documents have been approved by:


Georgia Department of Transportation (GDOT)

Federal Highway Administration


The realignment of Forest Hill Road/Wimbish/Northminster as proposed by Mr. Chellman in your response of March 19th has been considered by our group. Forest Hill Road carries about 1,000 vehicles per day (vpd) more than Wimbish Road. This would tend to make Forest Hill Road the dominant alignment. The current configuration of the two roads would provide the least detrimental impact to the community. To align Northminster Drive with Forest Hill Road would require displacement of a law firm and a mortgage association located on the corner. See the attached drawing labeled County Drawing No. 5. We would not recommend changing the alignment as per Mr. Chellman’s suggestion. As you already know, this intersection does not meet GDOT’s requirements for a roundabout.


Currently Forest Hill Road south of Wimbish Road is carrying some 14,869 vpd. It is projected to be carrying over 25,000 vpd in the design year (2024). Current GDOT policy requires that a raised median be placed on this type of facility. It also provides a landscaping opportunity to make the facility look more like a boulevard. Currently, Mercer University Drive from Log Cabin Drive to I-475 is having a raised median placed on it. I think Riverside Drive, which is under construction now, is probably a special case since access can only be made from the west side due to Interstate 75 being on the east side of the roadway.


I hope you will give these proposals your utmost consideration.



 





This webpage originates from some of the Mediators for the Friends of Forest Hill Road in Macon , Georgia.  It contains information which may be confidential or privileged and is intended only for the individuals or entity named above.  It is prohibited for anyone to disclose, copy, distribute, or use the contents of this webpage.  All personal messages are the express views of Concerned American Citizens and Taxpayers, and nothing here may be copied or distributed without their specific and individual permissions. 